CompTIA Project+ Test 2025 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 400

What is considered an output of the project planning stage?

A finalized budget only

A detailed project schedule and scope statement

The correct choice highlights that a detailed project schedule and scope statement are key outputs of the project planning stage. During this phase, project managers and teams work to establish the framework and parameters for executing the project successfully.

The detailed project schedule allows the team to outline timelines for various tasks, milestones, and deliverables, ensuring everyone understands when specific elements of the project should be completed. Meanwhile, the scope statement defines what is included in the project and what is outside its boundaries, clarifying the project's objectives, deliverables, and any constraints. These two elements together serve to guide the project’s execution and monitor its progress over time, making them critical outputs of the planning stage.

Other options do not capture the comprehensive aspect of the outputs from the project planning stage as effectively. For instance, while a finalized budget is significant, it represents just one component of the overall planning outputs. Identification of project team members is an essential activity, but it is part of the organizing rather than the planning outputs. Similarly, final risk evaluations are crucial for assessing potential project threats, but they are typically documented and addressed earlier within the planning stage rather than representing the end results of this phase. Thus, the combination of a detailed project schedule and scope statement most accurately embodies the outputs

Get further explanation with Examzify DeepDiveBeta

Identification of project team members

Final risk evaluations

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy